A tower crane is usually the tallest structure on a site, and sometimes in the whole neighbourhood. When the site is near an airport, a helicopter landing site or an area of aviation interest, the crane may be considered an aviation obstacle. In that case marking the crane for aircraft is required: warning lights for the hours of darkness, day marking in paint or flags, and prior coordination with the Civil Aviation Authority of Israel (CAAI). The guide explains when this is required, which lights are accepted, where they are fitted on the crane and what to prepare before erection.

This guide was reviewed by RMA’s engineering and service team. RMA has worked in tower cranes since 1981 and, as of 2026, provides ongoing service to about 500 cranes across the country. The binding requirement for every crane is set in the position of the Civil Aviation Authority of Israel (CAAI), so this article presents principles and sources and does not replace the Authority’s position or the project’s aviation consultant.

In brief

  • Whether a particular crane is an aviation obstacle is decided by its location, its height and its proximity to aviation infrastructure. In Israel, the CAAI decides.
  • For a crane or lifting rig, a request is submitted to the CAAI for its position on a “Tamir facility” (a tall, slender structure). Only after the location and height have been approved is a request submitted for publication of aeronautical information on the erection of a temporary facility.
  • The common lights are the L-810 steady red low-intensity light, the L-864 flashing red medium-intensity light and the L-865 flashing white medium-intensity light.
  • At least one light is fitted at the highest point, and additional lights at the ends of the jib and the counter-jib show the pilot the outline of the crane.
  • A common fault is lights going out when the crane’s main switch is turned off at the end of the working day. Plan a separate supply, a backup, a light sensor and a daily check.

When a tower crane counts as an aviation obstacle

Under Annex 14 of the International Civil Aviation Organization (ICAO), the assessment is made against the obstacle limitation surfaces defined around every airport, and against the height of the object above ground level. Aviation authorities also check the protection areas of communication, navigation and radar equipment, and the effect of the object on flight procedures. A tower crane is treated as a temporary structure with special characteristics: it stands on site for months and years, its height rises with every raising, and the jib slews and covers a wide area. To understand the orders of magnitude, it is worth knowing how several leading regulators treat cranes:

  • United Kingdom: under the interim guidance of the Civil Aviation Authority (CAA), a crane within 6 km of an airport and higher than 10 metres above the ground or the surrounding buildings and trees must be reported, as must any crane of 100 metres or more anywhere in the country.
  • Italy: under ENAC’s preliminary-check criteria, structures located in defined sectors around airports are checked, as is any structure 100 metres or more above ground. ENAC also asks to be notified when lighting is switched on and when temporary structures such as cranes are removed at the end of the works.
  • France: the one-stop window of the French civil aviation authority (DGAC) for obstacle matters includes a separate form for a “crane or temporary obstacle”, and explicitly mentions cranes near airports and helicopter landing sites.
  • United States: FAA Advisory Circular AC 70/7460-1M, as updated in October 2024, includes a dedicated chapter on temporary structures, including cranes, and states that each obstacle is assessed individually.

In Israel, the CAAI refers to the civil aviation interests map, which can be viewed in the Ministry of Transport’s Hatzav system and includes ground and airborne aviation infrastructure. It is important to remember that the height of the crane at the end of the project is higher than the height of the building, so approval of the height of the building itself does not necessarily cover the crane. It is worth checking this with an aviation consultant already at the crane placement planning stage.

ICAO principles: low, medium and high intensity

Annex 14 divides obstacle lights into three families. Each family is defined by colour, mode of operation (steady or flashing) and light intensity in candelas (cd) by day, at twilight and at night.

  • Low intensity: a steady red light. Type A at 10 cd at night and Type B at 32 cd. According to the annex, it is recommended for an object that is not extensive and whose height above ground is less than 45 metres.
  • Medium intensity: Type A flashing white (20,000 cd by day and at twilight and 2,000 cd at night), Type B flashing red and Type C steady red, both 2,000 cd at night. The annex recommends them for objects 45 to 150 metres high, and also for an extensive object of lower height.
  • High intensity: flashing white lights of up to 200,000 cd by day, intended mainly for objects above 150 metres. The FAA does not recommend them for temporary structures, including cranes.

In addition, under the annex at least one light is positioned as close as practicable to the top of the object, and medium-intensity flashing lights on the same object flash simultaneously.

Table: lights for marking a crane for aircraft

The names L-810, L-864 and L-865 are FAA classifications, and the lights are also marketed and sold in Israel under these names. The ICAO column gives the closest equivalent for orientation only. The binding light type, colour and position are set in the CAAI’s position.

LightColour and modeIntensity class (ICAO equivalent)Usual position on a tower craneNotes
L-810Steady red. There is also a flashing version, L-810 F, at 30 flashes per minuteLow, close to Type B (32 cd at night)Jib tip, counter-jib tip and points along the upper part. On a low crane, two or more at the highest pointAccording to the FAA, on a temporary structure up to 45.72 metres, two or more L-810 lights in the upper part are sufficient
L-864Flashing red, 20 to 40 flashes per minute (30 when combined with L-810 F)Medium, close to Type B (2,000 cd at night)The highest point of the craneThe FAA recommends it at the top of the crane, and on a temporary structure above 45.72 metres at least one in the upper part
L-865Flashing white, 40 flashes per minuteMedium, close to Type A (20,000 cd by day, 2,000 cd at night)The high point, when a warning is needed in daylight hours as wellThe FAA lists it as an addition or alternative to painting on temporary structures above 200 feet (about 61 metres)
L-856Flashing whiteHigh, Type AUsually not on cranesThe FAA does not recommend it for temporary structures

According to the FAA, on a temporary structure 45.72 to 106.68 metres high, intermediate levels of flashing L-810 F lights are added to the L-864 light at the top, and above 106.68 metres the intermediate levels are L-864 lights. All flashing lights on the same structure flash together.

Where to fit the lights on a tower crane

According to the FAA, the aim is to show a pilot approaching from any direction both the presence of the crane and its outline. On a tower crane this means three main points:

  1. The highest point. On a crane with a tower head, such as the Potain MD models, this is the top of the tower head. On a crane without a tower head, such as the MDT models, the high point is at the top of the slewing structure. This is usually where a flashing L-864 light is fitted, or a pair of L-810 lights on a low crane, according to the CAAI’s position.
  2. The jib tip. A steady light, usually L-810, marks the reach of the jib, which is the part a pilot finds harder to identify at night.
  3. The counter-jib tip. A light above the counterweight area completes the outline. The British CAA explicitly recommends lights at both ends of the jib to show the height and the shape of the crane.

On a tall crane, intermediate lights are added along the mast. According to ICAO, when the top is higher than 45 metres and is marked with medium-intensity red lights, the intermediate lights are spaced as equally as possible and no more than 52 metres apart. When the crane is surrounded by buildings, the height can be measured from the roofs of the adjacent buildings and not from ground level to determine the number of light levels.

A crane with a luffing jib

On a crane with a luffing jib, the high point changes with the angle of the jib. The FAA recommends mounting the lights on a swinging pivot, so that the light fitting stays level as the jib rises and is not hidden by the structure. In the request to the CAAI it is worth showing the maximum height at the highest jib angle, and not the height in a normal working position.

Raisings during the project

After every raising, the lights at the top and on the jibs rise with the crane, but new intermediate lights on the mast may be needed. The CAAI’s data sheet for a crane includes, among other things, the height of the crane above ground, the jib length and the date of dismantling. It is therefore worth submitting the planned final height in advance, and checking with the CAAI before any change of height or position that was not included in the position.

A jib that slews freely in the wind

At the end of the working day the slewing brake is released and the jib turns with the wind. The lights on the slewing part receive power through the crane’s slip rings, so it is important to make sure their circuit stays powered in this state too. The FAA stresses that from every approach direction the pilot should see at least one light without obstruction.

Day marking: colour, stripes and flags

Day marking is intended to increase the visibility of the crane in daylight. Under Annex 14, a fixed object that needs marking is painted wherever practicable. A lattice structure, such as a crane jib or mast, is marked with alternating stripes in contrasting colours, perpendicular to the long dimension. The width of each stripe is about one seventh of the long dimension or 30 metres, whichever is smaller. The recommended colours are orange and white, and the stripes at the ends are in the dark colour. The FAA recommends painting cranes aviation orange or in orange and white stripes, and accepts other conspicuous colours when flags or lights are present. By contrast, it recommends avoiding colours that blend into the background, such as light blue or dark green. Marker flags are fitted at the high point, each side of a flag at least 0.61 metres long, and a flag of 0.91 metres or more is checkered orange and white. The British CAA recommends stripes at least 5 metres wide, and notes that yellow and black, or yellow and dark blue, create a particularly strong contrast from the air, especially in an urban environment.

The process in Israel with the Civil Aviation Authority

According to the CAAI, section 94 of the Planning and Building Law requires notifying a body authorised by the Minister of Transport of the deposit of a plan that may affect civil aviation. Since Amendment 101 to the law, the CAAI is also integrated as an information-providing body in the licensing process, under regulation 16 of the Planning and Building (Building Permits) Regulations, 2016. The crane is handled on a separate track from the building, in the following stages:

  1. Preliminary check. Check in the Hatzav system whether the site is within an area of aviation interest, and consult an aviation consultant. The CAAI notes that it does not provide planning information as an alternative to professional advice, and recommends using a consultant familiar with aviation infrastructure and regulation.
  2. Request for the CAAI’s position on a Tamir facility. According to the CAAI, the right way to submit a request for a lifting rig or crane is the online form for obtaining a position on a “Tamir facility” (formerly called a “slender obstacle”), within the service for obtaining the Authority’s position on building restrictions. The request attaches a dedicated “lifting rig or crane” data sheet, which includes, among other things, coordinates in the New Israel Grid, ground level height, crane height, jib length and the date of dismantling. According to the CAAI, processing takes up to 45 working days from receipt of valid data.
  3. Receiving the position and its conditions. The position relates to the requested location and height, and may include conditions for marking, lighting and coordination. For example, in a project in Kiryat Motzkin reported in January 2026, the committee made the erection of the cranes conditional on CAAI approval of their height, marking and publication.
  4. Request for publication of the erection of a temporary facility. Only after a position approving the location and height has been received, a request is submitted for publication of aeronautical information to the pilot community, attaching the position document. According to the CAAI, processing takes up to 10 working days, at the end of which an approval for erecting the temporary facility is sent by email. The CAAI notes that a publication request is usually rejected when the wrong form was submitted instead of a request for a position on a Tamir facility.
  5. Erection and operation. The crane is erected at the approved location and height, it is confirmed that all the lights are on and documented, and it is clarified in advance with the CAAI whom to notify in the event of a lighting fault or a change in the plan.

The Standards Institution of Israel has published SI 5139, “Marking and lighting of aviation obstacles”. The current edition was published in February 2022 and was also published in the official gazette. The standard deals with the photometric, safety and environmental requirements for marking and lighting systems for aviation obstacles and the methods of testing them. In practice, it is worth asking the supplier for documentation showing which requirements the light meets. Coordination with the CAAI does not replace the obligations under the Safety at Work (Tower Cranes) Regulations, 1966. Draft amendments to the regulations were published for comment in 2022 and 2025, and as of October 2026 we have not found a final text published in the official gazette. Both subjects are also worth coordinating with the site safety officer.

Power supply, backup and light sensor

Obstacle lights need to work precisely when the site is closed: at night, at weekends and on holidays.

  • A supply separate from the main switch. The crane operator turns off the crane’s main switch at the end of the day. If the lights are connected after it, they will go out. The lighting circuit should be fed before the main switch or from a separate source, with clear signage that it must not be disconnected. The connection is made by a qualified electrician according to the crane’s electrical plan, and is included in the approval of the inspecting electrician. It is important that maintenance crews know that this circuit stays energised even when the main switch is disconnected.
  • Backup. The British CAA expects obstacle lighting to be connected to a secondary power supply, unless otherwise agreed with the competent body. On a day when the site is disconnected from the grid or the generator goes off, the lights must keep working. The common options are a backup unit with batteries, or solar lights with a built-in battery.
  • Light sensor. The FAA states that red lights should be operated by a control device, such as a light sensor (photocell) or a timer, which switches them on when natural light falls and off by day. They may also be left on continuously. It is worth positioning the sensor so that the site’s floodlights do not shine on it, because strong light may make it switch the lights off at night.
  • Synchronisation and additional lighting. Flashing lights on the same crane must flash together. According to the FAA, floodlights and architectural lighting may be added to the obstacle lighting, but must not replace it or hide it.

Maintenance and checking the lights

A burnt-out light at the top of the crane is not visible from the ground by day, so a fixed routine is needed. The FAA recommends checking the lighting visually at least once every 24 hours when there is no automatic monitoring, and keeping a log recording the state of the lighting each day. The FAA also says that a cracked, cloudy or dirty lens must be replaced, and a fault in a flashing light must be reported immediately and repaired promptly. In Israel, it is worth clarifying in advance with the CAAI the reporting procedure in the event of a fault. In practice we recommend checking all the lights after every raising, after a storm and after work on the jib, cleaning concrete dust from the lenses and keeping spare lights on site. Climbing to the top of the crane or to the jib tip is carried out only by workers qualified to work at height and with suitable protective equipment.

Common mistakes

  • Submitting a request for publication of a temporary facility before the CAAI’s position on the Tamir facility has been received.
  • Checking only the height of the building, without the final crane height and without the maximum angle of a luffing jib.
  • Connecting the lights after the crane’s main switch, so they go out at every disconnection.
  • A light sensor fitted facing a floodlight.
  • A light at the top of the crane only, without marking the jib and counter-jib tips.
  • Raising or relocating the crane without checking whether the change is covered by the CAAI’s position.
  • A light hidden by the crane structure or by a sign fitted on it.
  • No daily check and no lighting log.

A contractor’s checklist before erecting the crane

  • Check in the Hatzav system and consult an aviation consultant about the site location.
  • Determine the final height of the crane, including planned raisings and the maximum jib angle.
  • Prepare the data: coordinates in the New Israel Grid, ground level height, jib length and erection and dismantling dates.
  • Submit a request for the CAAI’s position on a Tamir facility, leaving enough time before erection.
  • After receiving the position, submit a request for publication of the erection of a temporary facility.
  • Plan the lighting points: top of the crane, jib tip, counter-jib tip and intermediate lights as needed.
  • Plan day marking if required: stripes, flags or a white light.
  • A separate supply from the main switch, power backup and a light sensor in the right position.
  • Document the lights fitted and test operation before handing the crane over for work.
  • Appoint a person responsible for the daily check, a lighting log and a fault-handling procedure.

Marking and lighting accessories for cranes at RMA

RMA supplies marking and lighting accessories for tower cranes, including the steady L-810 light, the flashing L-864 light and the solar L-865 light, and our service team fits the lights at height. The items can be seen in the marking and lighting accessories catalogue. If you are at the planning stage, you can contact us for a needs assessment and initial planning at no cost (an initial review of the site plan and a basic recommendation on model and position; a full placement plan is priced separately) and include the marking and lighting points in the placement planning already at that stage. The binding position on marking is set by the CAAI.

Frequently asked questions

Does every tower crane need an aircraft warning light?

Not necessarily. The need is determined by the location of the site, the height of the crane and the proximity to airports, helicopter landing sites and other aviation infrastructure. In Israel the decision is the Civil Aviation Authority’s, and the check starts with the aviation interests map in the Hatzav system and consultation with an aviation consultant.

What is the difference between an L-810 light and an L-864 light?

L-810 is a steady red low-intensity light, used mainly to mark jib tips and points along the crane. L-864 is a flashing red medium-intensity light, about 2,000 cd at night, and is usually fitted at the highest point of a tall crane.

Where is an L-864 light fitted on a tower crane?

At the highest point: the top of the tower head on a crane with a head, or the upper part of the slewing structure on a crane without a tower head. At the jib tip and the counter-jib tip, L-810 lights are usually fitted to show the outline of the crane. The binding position is set in the CAAI’s position.

How long does coordinating a crane near an airport with the CAAI take?

According to the CAAI, processing a request for a position on building restrictions, including a crane as a Tamir facility, takes up to 45 working days from receipt of valid data. After it, a request for publication of the erection of a temporary facility is submitted, and processing takes up to 10 working days. So it is worth starting the process long before the erection date.

Can solar lights be used to mark a crane?

Solar lights with a built-in battery are a common solution where running a cable is difficult, for example at the jib tip, and they also do not depend on the crane’s main switch. It is important to make sure the light meets the required intensity, that the battery lasts through the night even after cloudy days, and that the type suits the CAAI’s position.

What do you do when a warning light on a crane burns out?

Replace it promptly, by a worker qualified to work at height, and record it in the lighting log. The FAA recommends reporting a fault in a flashing light immediately and repairing it promptly. In Israel it is worth clarifying in advance with the CAAI the reporting procedure in the event of a fault, and keeping spare lights on site.

Does the colour of the crane count as day marking?

Sometimes. ICAO Annex 14 recommends alternating stripes in contrasting colours, usually orange and white, and the FAA also accepts other conspicuous colours when lights or flags are present. If the CAAI requires day marking, stripes, flags or a flashing white light may be required in addition to the original colour.

Sources and further reading

The information in this article is general and does not replace engineering, safety or legal advice for a specific site.