A tower crane base is the part that transfers all of the crane’s loads to the ground: the weight of the mast and jib, the load, the counterweights and the wind. The choice of base type affects the area the crane will occupy on site, the foundation costs and the schedule. In this article we explain the difference between a chassis and a foundation section, and when each method suits.
Static tower cranes, such as the Potain MD and MDT cranes in RMA’s rental fleet, are usually set up in one of two ways:
The Safety at Work (Tower Cranes) Regulations, 1966, generally require a static crane to stand on a stable foundation, with its stability secured by anchoring or another suitable method, and the counterweights to be positioned and secured properly. When the crane is placed on a building, the building must be strong enough for the crane, its operating range and the safe working load (regulation 35(b)). The engineering details are determined in the specific design for each site.
A chassis is particularly suitable when there is enough free area around the crane’s position on site. The main advantages:
The chassis counterweights arrive on site by truck and are put in place by a mobile crane. So access and working space for the crane and the trucks must be planned around the base too, and not only at the crane’s position itself. The number and weight of the counterweights are determined from the manufacturer’s data sheet for the chosen model and height.
The main drawback is the area: a chassis and its counterweights take up a significant area, and on dense urban sites that may be area needed for excavation, storage or vehicle movement.
A foundation section suits when space is limited, when the crane is placed inside the building footprint or in the excavation pit, or when there is no room for a chassis and its counterweights. The advantages:
On the other hand, a foundation section requires early planning, casting, and curing time for the concrete before erection. The anchor legs or the foundation section must be original manufacturer components for the specific mast, positioned with a location template and to the tolerances in the manufacturer’s instructions, and components that have already been cast into a foundation must not be reused. At the end of the project some components usually remain inside the foundation, and it must be planned how to close the opening in the building after the crane is dismantled.
The following figures are general ranges. The exact dimensions are determined by the crane model, its height and the manufacturer’s data sheet:
Beyond the base itself, allow for working clearance around it for erection and dismantling, and access for a mobile crane and trucks.
In either method, the foundation is designed by a structural engineer on behalf of the project. For the design to be accurate, the structural engineer needs the loads the crane transfers to the foundation, from the manufacturer’s data sheet for the chosen model, mast height and jib length. Points to coordinate:
RMA’s consulting team works with the structural engineer and provides the data needed for design. More details are on the consulting and planning of crane placement on a building site page, and in the article Planning crane placement on the building site.
| Criterion | Chassis with counterweights | Foundation section in a foundation |
|---|---|---|
| Area at ground level | As a rule about 4.5×4.5 to about 8×8 metres | As a rule about 1.6 to 2 metres (the mast cross-section) |
| Advance preparation | A slab or spot foundations | A concrete foundation with a cast section and curing time |
| Placement inside the building | Limited | Possible, in coordination with the structure |
| What remains at the end | Usually the chassis and counterweights are dismantled | Some components usually remain in the foundation |
| Particularly suited to | Sites with free area and short projects | Dense sites and placement inside the building |
RMA operates from a logistics yard in Lod. For information on base components see the mast sections, parts and chassis for cranes page. To coordinate the design, call 08-9202882 or send a WhatsApp message.
A chassis is a steel frame on which concrete counterweights are placed to provide stability. A foundation section is a mast section or anchoring legs cast into a concrete foundation, so the foundation itself provides the stability.
As a rule, a chassis takes up an area of about 4.5×4.5 to about 8×8 metres. The exact dimension is determined by the model and the crane’s height.
As a rule, the mast cross-section takes up about 1.6 to 2 metres, so a foundation section suits dense sites or placement inside the building.
A structural engineer on behalf of the project, based on the loads in the manufacturer’s data sheet for the chosen model, mast height and jib length.
With a chassis, the frame and the counterweights are usually dismantled. With a foundation section, some components usually remain inside the foundation, and the closing of the opening in the building must be planned in advance.
Yes, usually with a foundation section in the foundation, for example in a shaft or in an opening that will be completed later. This requires full coordination with the structural engineer.